Simon_
I have upgraded an old wylex CCU to modern and removed the separate Isolator box with a 40a rccb that was connected to a Henley block and then powering the shower from the CCU. The cable is 6mm and it's a Mira sport but fairly old. There was no shower switch so it was permanently on all the time and some of the cable was run on the outer wall of the house and back in the brick. Length from CCU to shower is approx 10-15m and obviously now a switch will be put in just before the bathroom. Was the Mira sport a specific kw to that model? It says on some sites that it's 10.8 kw in which case it will need a 10 mm cable and 45a mcb as it has a 240v sticker on the inside. I.R. Test on the old cable came back fine.