Paper work stage not installed yet.
We've had 30kw turned down in devon as it's not far from a multi-acre solar farm. Have been told by WPD that Devon and Cornwall is 'full'. Unlikely to be any private upgrades that will fix it, they reckon it will take billions in infrastructure upgrades.
we use power one with the PMU unit to control it, and elios 3 phase unit for the actual export limitation... it works, but waiting for a firmware upgrade to actually lock the setting.What make and type did you use to limit current capacity
if it is limited to 100amp.Spoke to Andy about the elios upgrade for 100 amp plus they have no intention yet to do so.
I need to limit 200 kw plus
bagsyFYI, 4-Noks are going to port across a similar system to the Elios PRO that they use in mainland Europe that allows export management for up to 200kW (maybe 250kW) systems, with security/lockout of parameters. It's an available solution but just not yet configured for the UK market. Would be handy to have an idea of potential demand though, although I know personally of multiple situations where this is required, and will probably be more frequently required as the grid gets more and more saturated.
Reply to Refused Connection in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net
We get it, advertisements are annoying!
Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.