Hi guys
SWA feeding outside lighting and socket outlets etc.
Set up like this:
Single phase.
L & N T&E out of MCB in main board to feed sperate enclosure with only an RCD module in. So L&N feeding an RCD.
Then, 4 core SWA is glanded to this board.
2 of the cores (L/N) connect to the Mains in side of the RCD (with the t&e)
The other 2 cores are on the load side of the RCD.
So, effectively 2 sets of L/N are taken to a junction box outside somewhere, where I assume one set that is unprotected go to outside lights and the RCD protected L/N pair are taken to socket outlets?
All of this controlled by 1 MCB
Is this correct, I can't really see why not?
SWA feeding outside lighting and socket outlets etc.
Set up like this:
Single phase.
L & N T&E out of MCB in main board to feed sperate enclosure with only an RCD module in. So L&N feeding an RCD.
Then, 4 core SWA is glanded to this board.
2 of the cores (L/N) connect to the Mains in side of the RCD (with the t&e)
The other 2 cores are on the load side of the RCD.
So, effectively 2 sets of L/N are taken to a junction box outside somewhere, where I assume one set that is unprotected go to outside lights and the RCD protected L/N pair are taken to socket outlets?
All of this controlled by 1 MCB
Is this correct, I can't really see why not?