i'd like to hear the other side to this story.
i cant see anyone walking away from a £12K job after a £3K deposit without a damn good reason.
and over 200 sockets ??? really ???
doubling the amount of power and lighting points in one go is gonna turn the design spec to crap with even the best electrician.
i suspect it was the reason above that gave the installer a bad vibe.
95 sockets in total and 210 lights. He must have his side to the story so it would be nice to hear it.
The way I see it:
65 sockets and 120 lights= £12350
That’s an average of £66.75 per item
He then accepted more work:
30 sockets at £25= £750
90 lights at £20= £1800
The new average is £21.25 per item for the extras
Based on the original price the cost of the extras should have been £8010 and not £2550. If I worked out I was going to rob myself of £5460, I would have walked too.
Maybe but no one in their right mind would pay 20k for 3 to 4 weeks work to wire up a single home. The original 12.3k included RCD's 30amp supplies.....
but if the 66/item includes accessories and the 21/item does not????. not enough info to make a solomon's decision.
I was going to supply all accessories.
SW1970 -All lights are going to be LED bulbs supplied by Rako 4 circuit racks in the server room.