Out of interest - how many people do you have on site for installation?

Tiled roofs we have 2 roofers for 3/4 day and a spark for 2, slate roofs we have 3 roofers for a day and a spark for 2 days.
 
Just 2 of us. Me doing electrics for however long it takes and my partner doing roof work for however long it takes. We then both get the panels up and fitted.
 
One of our electricians used to be a roofer so only need two Sparks, but we sometime mob the jobs by bringing guys in from our building business.
 
We have average 3 roofers - 2 sparks per job 9/10 done it the day.
this does chop and change but most cases

at first we where taking 2 days on any roof now we are taking less than 8 hours on any tile. slate / concrete ..

walk in the park now
 
We have average 3 roofers - 2 sparks per job 9/10 done it the day.
this does chop and change but most cases

at first we where taking 2 days on any roof now we are taking less than 8 hours on any tile. slate / concrete ..

That sounds like us really. If we had someone doing the running and always had 3 roofers we could do it in a day.
 
No average system is 4kw, either 16pannels or 22, most cable runs are external, start at 8 on the dot and don't do lunch breaks! Basically work like *+*^! But that's only because we have been doing this for quite a while and 1 a day for the last year or so!
 
Well obviously the rest of us must be lazy ;-). I must admit we rarely do external cable runs, but we've been doing this for 18 months now and can count on one had the number we've got done in one day. Mind you we do faff on making sure the customer is happy with the installation all along and we don't use click fit.
 
Pan-tile roofs, newish house - 1 day easily.
Slates/Rosemarys etc. - 2 days.

Of course, this all depends on deliveries. For whatever reason, moving a pallet of solar panels from a warehouse to our site seems to be an immensely difficult task.

I picture a scene like one out of Apollo 13 - a room full of baffled and panicked scientists gazing at monitor screens and scratching their heads.
 
I have two roofers and two electricians on each job and they are finished between 3pm and 5pm depending on size, most ofl our jobs are concrete tiles though so we do get it easy, for the first year it took upto two days so it is a matter of practice to some degree.
 
Last edited by a moderator:
On a more optimistic note - I positively skip to a tiled house to quote for it - might even be tempted to do Finchy's flash mob :clap:
 

Reply to How Many People on Site? in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net

Similar Threads

My best mate has been medically retired from the prison service at the young age of 52 and has time on his hands :D He's looking at a 'plug in'...
Replies
7
Views
423
I spend a lot of time renovating vintage broadcast radios, military radio and test equipment. At present adding panels to our off grid...
Replies
10
Views
1K
Hi I have three phase installed recently to increase generation. DNO approved the extra 2 solar arrays so we have 3.68KW FIT on one phase and 8KW...
Replies
1
Views
684
Have you got any plans for the long Easter weekend? Here in the UK Friday and Monday are both Public Holidays so a lot of people have a break or...
Replies
6
Views
190
Sorry if this is in the wrong place. I'm an electrician of 20 years. Starting out with domestic and commercial install work but mainly working in...
Replies
16
Views
2K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock