So spin, in the 18th it looks like they have combined the Ut and disconnection time into one reg.

Really since the 17th first came out the SB rules were relaxed in domestic subject to certain caveats (rcd being only one) which we were all glad about re: god awful G/Y everywhere in bathrooms ;), it is still a valid additional protective measure though elsewhere as always.

Ps. I was correct about the 25V Ut in agricultural in the 16th :)
 
Last edited:
So spin, in the 18th it looks like they have combined the Ut and disconnection time into one reg.

Really since the 17th first came out the SB rules were relaxed in domestic subject to certain caveats (rcd being only one) which we were all glad about re: god awful G/Y everywhere in bathrooms ;), it is still a valid additional protective measure though elsewhere as always.
Yes, it has made life easier.
Though there are two problems I have encountered.
One is that very rarely the Zs on some circuits of locations containing baths and showers, are not sufficiently low enough to allow ADS.
Two is that if there is no main bonding because of plastic services, can supplementary bonding still be omitted?
 
Probably, as plastic services mean that caveat no longer applies in most cases, and we are now reying solely on RCDs ;) , god how I wish the IET would sort their existing s**t out before introducing new regs ;)
 
As another poster earlier had said re: 'ductor testing joints in conduit, I have had to do this twice back in the day, what a mind numbing and boring job that was :(
Later with more modern MFTs that cut-out if the CPC rises above 50V (or 25V if you set it up that way) we have on occasion just used a hi-current loop test to check for reasonable integrity, no other test was specified in this case, so it was better than relying on a 20mA continuity test only in the first instance.

Ps. did the continuity test first btw
 
Last edited:

Reply to How to test a circuits in steel conduit as the cpc in the Electrical Forum area at ElectriciansForums.net

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Electrical Forum

Welcome to the Electrical Forum at ElectriciansForums.net. The friendliest electrical forum online. General electrical questions and answers can be found in the electrical forum.
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock