hi all
a couple of questions for 2391
1. What must be agreed with the client in relation to the timing of the inspection

2. how the agreement in 1 above may have an effect on live testing at the origin of the installation

3. state why accurracy checks, in addition to calibration, should be carried on a inspectors test equipment

4. two possible consequences if these accuracy checks are carried out regulary

thanks to all
 
hi all
a couple of questions for 2391
1. What must be agreed with the client in relation to the timing of the inspection

2. how the agreement in 1 above may have an effect on live testing at the origin of the installation

3. state why accurracy checks, in addition to calibration, should be carried on a inspectors test equipment

4. two possible consequences if these accuracy checks are carried out regulary

thanks to all

1 Timings to lessen impact of testing on clients buissness

2 Out of hours testing may be required as to lessen need to unpug vital equipment while in use

3 to maintain acuracy and consistancy of results

4 possibly wrongly put shouldnt it be "Are NOT carried out"? if so then Id answer
4.1 inconsistant results
4.2 possibly catching damage to tester before it causes major faults
 
1 Timings to lessen impact of testing on clients buissness

2 Out of hours testing may be required as to lessen need to unpug vital equipment while in use

3 to maintain acuracy and consistancy of results

4 possibly wrongly put shouldnt it be "Are NOT carried out"? if so then Id answer
4.1 inconsistant results
4.2 possibly catching damage to tester before it causes major faults

Thanks a lot mogga
yeah the fourth question should say are not carried out
cheers mate got me exam thursday so just going through everything for about the 1000th time and still things catching me out thaks again mate no doubt there will be more questions yet
thanks again

oh just thought of 1
three examples of a exposed conductive parts that may need to be inspected in a wharehouse
 
Last edited:

Reply to timing of inspections in the Electrician Courses : Electrical Quals area at ElectriciansForums.net

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock