Hi,


Mainly been doing domestic installations so far, some small scale commercial still G83.

Finding it a bit of a nightmare gathering all the information and pricing I need to accurately quote for larger size systems.

I think i'm nearly there...

-We will be getting our assessors to measure and quote based on the size system;
-If the customers happy we get a Letter of Authority to apply to local DNO for G59 connection;
-Send application with relevant info on form etc and wait for response;
-Either receive decline, approval or approval with network upgrades (additional costs);
-Hopefully it is a straight approval (so should be free of charge) in which case can get to work installing said system once contract signed;
-Once installed (with approved materials) contact chosen G59 Relay supplier to install and test G59 Relay (Cost for G59 Relay and equipment + Cost for Testing) (May require witnessing by DNO at a cost);
-Send filled in (by G59 test engineer) 'Generating Plant Installation & Commissioning Confirmation' to DNO;
-If system over 30kW then export meter required, in which case;
-Contact FiT provider to find out relevant Meter Operator;
-Contact Meter Operator to fill in Half Hourly Meter Operator Contract Form which provide an Export MPAN (Cost to install + yearly meter costs);
-Register Export MPAN with FiT provider and get approval (Quarterly costs for data provision);
-Meter Operator then fits new or replaces existing Import Export Meter;
-Wait for completion of set up.

If under 50kW register with MCS, and over with RO.

I haven't specified the costs of the Relay, testing, export meter and data provision as i don't know the costs.

The question is,
Is that everything?

Or have i missed anything out that could pop up unexpected down the line or got anything wrong?
 
You don't have to meter if >30kWp TIC, just if you want to avail of the export tariff. G59/3 relay may not be required if inverters are <50kW and there's no more than 5 of them - that's not written in stone and will/may vary from DNO to DNO, project to project.

If you need any pricing or assistance then by all means give us a shout. We can help if you are restricted on export too...
 
You don't have to meter if >30kWp TIC, just if you want to avail of the export tariff. G59/3 relay may not be required if inverters are <50kW and there's no more than 5 of them - that's not written in stone and will/may vary from DNO to DNO, project to project.

If you need any pricing or assistance then by all means give us a shout. We can help if you are restricted on export too...


Thanks for the info!
Interesting point about not needing a meter for over 30kW, I guess it will come down to whether the costs are worth while for the export.

Out of interest what assistance do you provide on pricing or on restricted export? (Intrigued)


Thanks
 
"-Contact FiT provider to find out relevant Meter Operator;"

Which Meter Operator you use is just a decision that the customer can take. It is not up to anyone to tell you who you can and can't use.

You simply need to find an accredited company that do what you want in your location. But the big 6 do have their own MOP divisions and will steer you in their direction if they are asked, maybe without giving you all the options.

The customer may have their own preferred MOP if they already have HH metering for import so it would usually make sense to use that same company to handle the export metering as well.
 

Reply to G59 & Export Metering Process in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net

Similar Threads

Hi all I had my PV/Battery setup installed in May and since then all my excess PV is just fed back to the grid for free. When I initially tried...
Replies
1
Views
2K
Hi, Similar'ish question to my other thread but little more info now so a different approach but sorry if duplication. UK, single phase. Just had...
Replies
0
Views
1K
V.early days, just had installed solar. No battery, also supply of some parts difficult at the moment so no App or Online monitoring. I have a...
Replies
3
Views
3K
So I am a fully qualified spark with my own company, however I also have a few properties I rent out. One of my tenants asked if they can have an...
Replies
84
Views
10K
Hello all, I've just been perusing the AM2/E/S threads on here. Thought you might like a bit of a review. If, like I did, you find yourself...
Replies
7
Views
2K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock