Hello All,
New to the board, but a great resource for new installers.
We are about to due a slightly larger job than our usual 4kW install. The install is for a 17.1kW system. As the building has two meters, we are going to split this install so that the user can benefit from a better FIT tariff e.g. 9.1kW and 8kW.
We are going to use 3-phase inverters for this job and I was wondering what would be the correct form to download for this.
I have been sent 2 links. The link below however says G83 but i thought it would come under G59?
http://www.ukpowernetworks.co.uk/products-services/networks/pdf/G83_multiple_installation_application_form.pdf
When I called the DNO and informed them about the install, they emailed me the following
ENA am hoping its the first form that needs to be filled out as the second form has me puzzled.
Can someone guide me in the right direction.
UK power networks is the correct DNO I need to inform about the job.
Thanks for the input.
New to the board, but a great resource for new installers.
We are about to due a slightly larger job than our usual 4kW install. The install is for a 17.1kW system. As the building has two meters, we are going to split this install so that the user can benefit from a better FIT tariff e.g. 9.1kW and 8kW.
We are going to use 3-phase inverters for this job and I was wondering what would be the correct form to download for this.
I have been sent 2 links. The link below however says G83 but i thought it would come under G59?
http://www.ukpowernetworks.co.uk/products-services/networks/pdf/G83_multiple_installation_application_form.pdf
When I called the DNO and informed them about the install, they emailed me the following
ENA am hoping its the first form that needs to be filled out as the second form has me puzzled.
Can someone guide me in the right direction.
UK power networks is the correct DNO I need to inform about the job.
Thanks for the input.