Hi
Looking for some advice please.
I started renovating my house in 2015 and as part of this I ripped out all the wiring and got my electrician to rewire it including a new plastic consumer unit. There is still some electrical work to do so none of it had been signed off yet.
As the plastic consumer unit was fitted prior to the regulation change I’m assuming that it doesn’t need replacing with a metal one to be signed off. Am I correct? Thanks.

Chris
 
The only exception to that particular reg, was whether the installation was designed before the applicable date. Typically with new build sites.

A one off installation, I’m not sure you would get away with that? When was the plastic consumer unit installed?

5 years in the making, is quite some time!
 
It applies to jobs where the design was started under one set of regulations, then it doesn't have to be changed to reflect new regulations - usually applies to flats or large installations though and it may be stretching it a bit for a single dwelling, but in theory if the electrician is happy to sign it off and state on the certificate that it was designed to 17th Edition Amendment 2 then he can do so. I think the metal consumer unit requirement came in January 2016.

The issue may be more than the consumer unit change should have been notified to the council under Part P at the time (or within 28 days of the work). If that was done, then that part of the job can be considered to have been signed off at the time so shouldn't be an issue.

There is no immediate requirement to change a plastic consumer unit if adding a new circuit to it with recent works (with various caveats such as it being in good condition etc).
 
Thanks for the replies.
Yes, 5 years is a while but it was a bungalow that was gutted, extended and had an upstairs added. I’ve done most of the work on my own and had to start bringing some money in again after the first 2 years. Poor health has slowed me down a bit recently as well. Thankfully I’ve got a reasonably patient wife.

The consumer unit was fitted in mid 2015 along with the majority of the wiring. The unit met regulations when it was fitted but as there is ongoing work, nothing has been signed off. My electrician has been fantastic, couldn’t have asked for more from him but was a bit surprised when he told me that the consumer unit would now need to be upgraded to a metal one. I know he’s not trying to rip me off but just wondering if maybe he’s got his information wrong on this occasion.
Thanks again.
 
Hi - I agree with your Electrician. The EIC is to certify that new electrical installations are designed, installed and tested prior to them being commissioned. So there is an element of timeliness involved and 5 years is way past that, sorry. I complete an EIC (and Part P approval) when the CU is changed. Then further EIC are done as work is completed and commissioned.
 
Ok. Thanks guys. Shouldn’t take him long to swap them over the speed he works at and the plastic one can be used in the garage when I get around to it, unless they change the regs again.
 
all he needs to do is change the box, refitting the guts from the existing plastic box.
 

Reply to Plastic to metal consumer unit in the UK Electrical Forum area at ElectriciansForums.net

Similar Threads

Ok, most new Consumer unit seem to come with a 63A RCCB and two MCBs. Most house consumer units now will also have RCD of some type be it a dual...
Replies
24
Views
1K
In a property with two consumer units one for the ring main etc., and the other for the 1970s storage heaters (storage heater CU looks like it’s...
Replies
14
Views
1K
Hi, I've done some work in a house, I used an existing 10mm cable on a B40 MCB to supply a 2 way consumer unit to control a heat pump and...
Replies
1
Views
999
Completed my AM2s start of this year. My whole career plan is to run my own company/sole trader. Be my own boss basically. I always get asked...
Replies
14
Views
699
I live in a flat in Scotland supplied with an old 2 meter system called THTC where one meter using a time signal supplied heating and hot water...
Replies
7
Views
1K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Electrical Forum

Welcome to the Electrical Forum at ElectriciansForums.net. The friendliest electrical forum online. General electrical questions and answers can be found in the electrical forum.
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock