Hi all.
I have two questions if anyone can help.
1st. Has anyone installed Enphase micros to a three phase system. I can't find much info on the internet. How does the Envoy communicate with the micro inverters as you can only plug it into one phase at a time. The nearest ring main to DB is on...
Hi guys
Is it possible to use 2 strings through one isolator. For example 2 no 820v strings..trying to clear up a disagreement. 1000v isolators used. Thanks in advance and when is 3rd edition of the pv guide coming out ???
I'm Niceic for part P and Napit for MCS (more badges for van) so correct me if i'm wrong, I just register the AC stuff though Niceic as I always have done and MCS for PV. If I get tokens now how long before I get certificate. This is the first paid job and one more next week so I need to get...
Hi. Registering first job. I thought it was 5 quid per registration. I'm with Napit and it costs £15 per token. Been a long day and just finished. Am I missing something
Therefor, if the installation was registered and the inverter failed and subsequently replaced, what is the difference. Not trying to be fraudulent, It was intended to be hypothetical
Just about to be enrolled on register (MCS). Cost so far £6000 plus (one man band) and not a penny turned over. I have been given an opportunity to do some subbing and they have supplies except for inverters. Believe they use SMA's and nothing else !!!!!!. Being in at the beginning of the end...
Its getting late now and i'm tired. I cant remember the facts and figures but wasn't the FITs brought in to encourage people to invest in PV so they could help bring emissions down and meet targets that have been promised. I heard they had to install a minimum of 1700 systems a day by 2020 to...
Agree to a point. But correct me if I am wrong. I we not to accept manufacturers recommendations above any regulations current. Thereby passing the buck to them. Just another paper trail exercise. Not that I agree with it of coarse.
Hi Worcester. Any chance of risk assessment too. Got my assessment next week and just dotting the I's and crossing the t's. Many thanks in advance. [email protected]
I had a similar experience. It took me 3 weeks of constant harrasment and complaining to get the manual sent. After which they told me the assessment date would be 10-14 weeks. That means it could have been a total of 17 weeks. Initially they told me 6-8 weeks from time of payment. Alarm bells...
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.