Discuss 2396 Design exam help on processes in the Electrician Courses : Electrical Quals area at ElectriciansForums.net
Take my advice, even if you dedicate a couple of hours a week stick to it. I aimed to complete mine within 6 months and it still took me a year.Not sure on the pass mark this time round, maybe the report will be out soon. Didn’t like to ask tutor how others had got on.
I made a very brief start on the project, answers first couple of questions and began sourcing some suitable luminaries etc. But towards end of the course I decided it was best to focus on the exam, no point going too far with project if I hadn’t got through that!!
Just need to get my head down now between work and family and start chipping a few hours off.
Electrical Training Centre!What type of building are you designing for your project ?
Depends on what they are asking for. If they are only asking for wiring routes don't worry about cable drops etc. I went down my local stationary shop and got some of the drawings printed out on A3 and A2. I had quite a few A3 sheets used for rough drawings and routes.Thanks for that Strima. How did you go about showing the wiring routes on the drawing, did you simply have line after line in a different colour showing the intended routes down to switches and then back to the luminaries? Or did you split lighting and power? I’m think I’m mainly a little unsure just how much details they’re looking for and I don’t want to spend time going ott or perhaps worse, having to go back over it again because I’ve not covered enough!
Do you have past exam papersHi
I am resitting my 2396 tomorrow and going through my past papers I have a question that I stumbled on last time out. The training provider I failed with are no longer in business, they weren't very good, so I am on my own.
The questions are ;
A 230v single phase circuit is wired using a multicore 70c thermoplastic cable having 1.5mm2 conductors and 49m in length.
It is protected by a 16a BS88c,PScc reading at the origin of the circuit is 110a.
Q. Determine if this circuit has adequate short circuit protection?
And -
Q. How do you determine if a circuit breaker will protect the live conductors in line with 434.5.2?
Not necessarily looking for answers but a breakdown of the process would be greatly appreciated.
Thanks
Chris
Chris do you have past exam papers.Hi
I am resitting my 2396 tomorrow and going through my past papers I have a question that I stumbled on last time out. The training provider I failed with are no longer in business, they weren't very good, so I am on my own.
The questions are ;
A 230v single phase circuit is wired using a multicore 70c thermoplastic cable having 1.5mm2 conductors and 49m in length.
It is protected by a 16a BS88c,PScc reading at the origin of the circuit is 110a.
Q. Determine if this circuit has adequate short circuit protection?
And -
Q. How do you determine if a circuit breaker will protect the live conductors in line with 434.5.2?
Not necessarily looking for answers but a breakdown of the process would be greatly appreciated.
Thanks
Chris
Email address removed. The original poster has not been seen for nearly three years so you are not likely to get a response.Chris do you have past exam papers.
Leo
Reply to 2396 Design exam help on processes in the Electrician Courses : Electrical Quals area at ElectriciansForums.net
We get it, advertisements are annoying!
Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.