sedgy34
We have a 12kw and 2 x4 kw all on same building still under G83 DNO said just do it and let us know on commission
Discuss Dno nightmare what do i do? in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net
you want to have some words with NIC, as it's not been like that for several years.in my training manual for niceic solar course i did a year ago it says
when installing a pv system under g83/1 for single installations the relevent dno must be notified at/before commisioning then g83/1 appendix 3 paperwork handed in before 28 days from install and this is what i did notified them that i was installing a 4kw system with a g83/1 inverter is this not the case? has this changed
@sedgy34, you have to remember that you are in the old Central Networks area, now Western Power Distribution and they are probably the easiest DNO of all to work with.
you want to have some words with NIC, as it's not been like that for several years.
Reply to Dno nightmare what do i do? in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net
We get it, advertisements are annoying!
Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.