Hi again guys.
So, if you're filling out EIC + Sched Of Inspections + Sched(s) of Test for an existing installation, for example because you've added new circuits :-
1. When filling out the Sched Of Inspections, do you fill it out thinking about the new stuff you've put in or the whole installation? For example the SELV box: if my additions feature no SELV but the existing installation does, is that tick or N/A? Another example, the one that's got me a bit foxed, the "Routing of cables in prescribed zones" box: well, none of my additions are buried so zoning is N/A for them...but much of the wiring of the pre-existing circuits is buried...haven't noticed any buried outside the zones but cannot say with authority that all that's buried is within the zones...so should that be tick or N/A?
2. Testing: I take it there is no hard and fast obligation to test existing final circuits where your additions neither interfere with them not rely on them?
Cheers guys, much appreciated.
So, if you're filling out EIC + Sched Of Inspections + Sched(s) of Test for an existing installation, for example because you've added new circuits :-
1. When filling out the Sched Of Inspections, do you fill it out thinking about the new stuff you've put in or the whole installation? For example the SELV box: if my additions feature no SELV but the existing installation does, is that tick or N/A? Another example, the one that's got me a bit foxed, the "Routing of cables in prescribed zones" box: well, none of my additions are buried so zoning is N/A for them...but much of the wiring of the pre-existing circuits is buried...haven't noticed any buried outside the zones but cannot say with authority that all that's buried is within the zones...so should that be tick or N/A?
2. Testing: I take it there is no hard and fast obligation to test existing final circuits where your additions neither interfere with them not rely on them?
Cheers guys, much appreciated.