Hi, I’m after a bit of advice with regard to completion of part of the “supply & particulars” section of an EIC for a slightly unusual domestic property.
There is a 3 phase supply to a detached building on site, from where L1 is used to supply three separate single phase consumer units (garage, flat, main house). The three phases are used to supply a sewerage pump on site.
Work completed to relocate and replace one of the single phase CUs, including new switch fuse/new SWA supply from origin of supply, plus work to its circuits.
Firstly, am I right in recording this as a three phase supply on the EIC?
Also do I take into account the other two consumer units when calculating the maximum demand or keep it specific to this consumer unit?
Many thanks
Alan
There is a 3 phase supply to a detached building on site, from where L1 is used to supply three separate single phase consumer units (garage, flat, main house). The three phases are used to supply a sewerage pump on site.
Work completed to relocate and replace one of the single phase CUs, including new switch fuse/new SWA supply from origin of supply, plus work to its circuits.
Firstly, am I right in recording this as a three phase supply on the EIC?
Also do I take into account the other two consumer units when calculating the maximum demand or keep it specific to this consumer unit?
Many thanks
Alan