- Reaction score
- 106
I did a job recently changing some faceplates. Owner was concerned about insulation above his new spotlights. Over some the insulation wasn't put back at all - a whole section was moved and not put back. Other spotlights had been covered. Also no jbs used so inner cores exposed and no cert. Took the guy 3 days to put 14 spots in 3 rooms, one external light and one external socket. The so called sparks promised a cert but nothing turned up.
Customer supplied the spots and external light and socket. So called sparks supplied everything else and labour for 350
I ended up sorting the mess out and the customer realised that the cheapest isn't always the cheapest and was out of pocket.
Customer supplied the spots and external light and socket. So called sparks supplied everything else and labour for 350
I ended up sorting the mess out and the customer realised that the cheapest isn't always the cheapest and was out of pocket.