Hi Guys
Done CU (peak & off peak) upgrade last week, they've got EDF Economy 7.
E7 only does an overnight immersion, rest of property is on the peak supply.
Had call from customer saying E7 overnight immersion is not coming on ? Just trying figure out what may have happened.
Tested out at time IR and R1+R2 all good.
Any ideas please would be appreciated ?
Didn't touch any of the tails linked to time clock.
As had power off for 4-5 hours could this have 'upset' the time clock somehow ?
Thanks Sy
Done CU (peak & off peak) upgrade last week, they've got EDF Economy 7.
E7 only does an overnight immersion, rest of property is on the peak supply.
Had call from customer saying E7 overnight immersion is not coming on ? Just trying figure out what may have happened.
Tested out at time IR and R1+R2 all good.
Any ideas please would be appreciated ?
Didn't touch any of the tails linked to time clock.
As had power off for 4-5 hours could this have 'upset' the time clock somehow ?
Thanks Sy