Out of interest, why did they want a different electrician doing the remedials?
I think he just wanted some quotes for the remedial work from different electricians.
Discuss Went to quote, discovered recent EICR has fabricated results. How to proceed with client? in the UK Electrical Forum area at ElectriciansForums.net
Out of interest, why did they want a different electrician doing the remedials?
It is the trend nowadays to get different electrician as there is a conflict of interests in EICR and remedials.
nothing wrong with you doing remedial works. these are not subject to part pee unless you need to add a new circuit/change a DB/alter wiring in a special location/install electric UFH.When I do EICRs, it’s on the basis that I just do the inspection and make the report.
I’m not Part P registered so I would tell them I can’t do any of the remedial work.
I have done some stuff, such as blank off a socket, add an RCD socket, mark up switch wires, put labels on CUs, sleeving on CPCs, etc.
I feel it’s better for them to know, I’m not touting for work.
No there’s nothing wrong with me doing them.nothing wrong with you doing remedial works. these are not subject to part pee unless you need to add a new circuit/change a DB/alter wiring in a special location/install electric UFH.
I’m not Part P registered so I would tell them I can’t do any of the remedial work.
I’m not Part P registered so I would tell them I can’t do any of the remedial work.
Reply to Went to quote, discovered recent EICR has fabricated results. How to proceed with client? in the UK Electrical Forum area at ElectriciansForums.net