I have a agreed on site with electrical foreman to install 48 way dist. boards on 8 floors. We both agreed on a horizontal 4"x 4" header(approx. 400mm long) on top of board with a 600mm stem 4"x 4" stem into header thus forming a tee. This was in plastic although my own preference would be metal trunking. The boards were fed in t&e approx. 17 lighting circuits 1.5mm . 6amp ,18 radials 2.5mm sockets 16amp and 6 cookers 10mm.Some rooms have heaters small loading, i think . When cables are compressed into trunking there is at least 50% excess space left . Apart from the short trunking above board the cable mainly runs on basket for about 20 metres and through a wall passing into 300m of plastic pipe filled with firestop.I have installed this on five floors .Now some buffoon , a so called sparks has said that because of grouping there should not be the 600mm of vertical trunking above the board as there is not enough space for grouping!!!!! But keep horizontal bit, ha ha. I find this absurd as it is such a small length and there is still 50% capacity for more cables anyway.If anything the cables passing through wall filled with firestop would be susceptible as there is no air gap at all !!!!! .Help would be much appreciated as I think it absurd to change what I have done .
 
the other chap appears to be talking crap but thats not the issue
the issue is what authority does this person have over your work ?
is the foreman gonna back you up ?
and are you following design / instruction from another party ?
 
Thanks biff ,the other guy is just an agency sparks with a so called 2391 such as I have. What makes me laugh was the .I feel he is trying to interfere as he likes control of the job. Has been on the job a month or so longer and creates paranoia .The laughable thing is the owner /director of the company employing us did see the install only an hour or so earlier and did not mention a thing!!!!!!! and definitely seemed happy with it.There is NO SPEC. with the job it is make it up as you go along.
 
Thanks biff ,the other guy is just an agency sparks with a so called 2391 such as I have. What makes me laugh was the .I feel he is trying to interfere as he likes control of the job. Has been on the job a month or so longer and creates paranoia .The laughable thing is the owner /director of the company employing us did see the install only an hour or so earlier and did not mention a thing!!!!!!! and definitely seemed happy with it.There is NO SPEC. with the job it is make it up as you go along.I thought you made the cable calcs. before you installed the cable anyway lol ??????? as he was also worrying about volts drop in certain other area's, more medicine matron lol !!!!!!
 
Last edited:
ah , so its the old design and build type contract where the client doesnt want to pay for proper plans for the job and expects the hired help to knock together the installation for him.

in which case all bets are off , and you can do it as you see fit without fear of comebacks.
just ignore the other spark hes just trying to points score to look clever.
 

Reply to grouping urgent question in the Electrical Wiring, Theories and Regulations area at ElectriciansForums.net

Similar Threads

Hi everyone Ive just had an electrical condition report conducted on a mixed-use property, and I am extremely surprised that after the last report...
Replies
11
Views
2K
Hello all, I've just been perusing the AM2/E/S threads on here. Thought you might like a bit of a review. If, like I did, you find yourself...
Replies
7
Views
2K
  • Locked
Hi, we need some advice on our scenario with regards to our rewire plan. I will get this out of the way first... We are planning to put the house...
Replies
24
Views
5K
Hello, Whilst doing some building works I have access to the inside of the stud wall to which the consumer unit is fitted, so full and easy...
Replies
22
Views
4K
Hello Everyone, I am not sure of the etiquette here on the forum, but I would like to start by extending warm greetings to everyone in the house...
Replies
167
Views
21K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock