wall paper should have been removed before plastering. should never plaster over paper. a plasterer can have a brain transplant upgrade to a kitchen fitter for £5000. cost recovered on first fitted kitchen ( minus the sparks's charge for repairing drilled cables ).well he actually plastered over the wallpaper in a few places so when we have removed the wallpaper its either failed or exposed a seam between them. im going to just re skim over it to take it back to flat again
I know, OP was asking is it needed it. If not in a zone it needs to be ran in earthed conduit complying with BS EN 61386-21.If they weren't run in prescribed zones then capping would make no difference at all. Daz
irrespective of whether or not cables are mechanically protected as you say, they still must be routed in prescribed zones. just a shame that plumbers, kitchen fitters and builders ain't got a clue about the zones.I know, OP was asking is it needed it. If not in a zone it needs to be ran in earthed conduit complying with BS EN 61386-21.
I learned my lesson last time I thought metal capping would be sufficient from @Taylortwocities
Reply to Just had full rewire done, cables very close to surface or coming through skim in the UK Electrical Forum area at ElectriciansForums.net
We get it, advertisements are annoying!
Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.