claret73
I did find the answer pretty much to this in an old thread & was answered by Chris...
But wonder if I could get a few more suggestions as to being correct.
Installed a Main Water Bond from a DB Board to the Main Incoming water supply which was (in my opinion) well over 25m away. We ran it along the existing SWA supplying the Workshop/Garage. It was run in 10mm.
No Test was carried out to confirm the 0.05 Max reading and from what I can figure am not sure if the cable has a high enough CSA.
In OSG I see an R2 reading on 10mm at 20deg of 0.00183 (even though the cable is run outside for most of its length), again from Chris's answer I can only have 27m before 0.05 resistance is breached.
I'm right in saying anything over 27m needs to step up to 16mm.
If the resistance is above the 0.05 does this have no barring consequences as to the potential difference between exposed & extraneous parts? Can't seem to find the exact clarification on this.
Cheers
But wonder if I could get a few more suggestions as to being correct.
Installed a Main Water Bond from a DB Board to the Main Incoming water supply which was (in my opinion) well over 25m away. We ran it along the existing SWA supplying the Workshop/Garage. It was run in 10mm.
No Test was carried out to confirm the 0.05 Max reading and from what I can figure am not sure if the cable has a high enough CSA.
In OSG I see an R2 reading on 10mm at 20deg of 0.00183 (even though the cable is run outside for most of its length), again from Chris's answer I can only have 27m before 0.05 resistance is breached.
I'm right in saying anything over 27m needs to step up to 16mm.
If the resistance is above the 0.05 does this have no barring consequences as to the potential difference between exposed & extraneous parts? Can't seem to find the exact clarification on this.
Cheers