I dont remember meters being mentioned, How are you intending on doing this?, it opens a whole can of worms now. are you having your own meters installed and charging your tenants yourself or are you intending on having prepay meters, if its pre pay then the DNN must install them and their own Ryefield to supply them, and that will be big cost!.
If you are having meters in the switch room then you are back to Ryefield - meter - switch fuse - galv - swa and with all of that you will need a switch room the size of a bedsit for all of that 12 x over
if you are having the meters in the bedsits then the hager solution will work. you can get cu's to go in the bedsits that have meters built into them, so it would be
Cutout - hager - swa - cu with integral meter.